Structure:
Raft - 100% completed
Basement Slab - 100% completed
GF to 17th Floor Roof Slab - 100% completed
SHR, OHT & LMR - 100% completed.
Finishing:
1st to 17th floor - Block work - 100% completed
102/105 - Internal plaster - completed
External Plaster:
Flat - 1 Series - 1st floor to 17th Floor Completed
Flat - 2 Series - 1st floor to 17th Floor Completed
Flat - 3 Series - 1st floor to 17th Floor Completed
Flat - 4 Series - 1st floor to 17th floor completed
Flat - 5 Series -1st floor to 17th floor completed
Flat - 6 Series - 1st floor to 17th Floor Completed
Activities in progress
Finishing:
Internal Plastering works
-
Tower-B2 Last Updated:31 March 2023 DescriptionTower-B2Activities Completed
Structure:
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 17th floor Roof Slab - 100% completed
SHR, OHT & LMR - 100% completed.
Finishing:
1st to 17th floor Block work - 100% Completed
103/104 - Internal plastering - Completed
External Plaster:
Flat - 1 Series - Ground floor to 17th floor completed
Flat - 2 Series - Ground floor to 17th floor completed
Flat - 3 Series - Ground floor to 17th floor completed
Flat - 4 Series - Ground floor to 17th floor completed
Flat - 5 Series - Ground floor to 17th floor completed
Flat - 6 Series - Ground floor to 17th floor completed
Activities in Progress:
Finishing:
Tiling Works - 32/104 Completed.
Waterproofing Works - 42 /104 flats Completed
Internal Painting
-
Tower-B3 Last Updated:31 March 2023 DescriptionTower-B3Activities Completed
Structure
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 17th Floor Roof Slab - 100% Completed
SHR, OHT & LMR - 100% completed.
Finishing:
Ground floor to 17th floor block work - 100% Completed
105/105 - Internal plastering - Completed
External Plaster:
Flat - 1 Series - Ground floor to 17th floor completed
Flat - 2 Series - Ground floor to 17th floor completed
Flat - 3 Series - Ground floor to 17th floor completed
Flat - 4 Series - Ground floor to 17th floor completed
Flat - 5 Series - Ground floor to 17th floor completed
Flat - 6 Series - Ground floor to 17th floor completed
Tiling works - 105/105 flats completed Internal Painting -105/105 Units Completed
Apts Handing over-105/105 completed
External Painting
External Painting - 100% Completed
-
Tower-C1 Last Updated:31 March 2023 DescriptionTower-C1Activities Completed Structure
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 17th floor Roof Slab - 100% Completed
SHR, OHT & LMR - 100% completed.
Finishing:
GF to 17th Floor Block work - 100% completed
Internal Plaster - 104/104 flats completed
External Wall Plastering
Flat - 1 Series - Ground floor to 17th floor completed
Flat - 2 Series - Ground floor to 17th floor completed
Flat - 3 Series - Ground floor to 17th floor completed
Flat - 4 Series - Ground floor to 17th floor completed
Flat - 5 Series - Ground Floor to 17th Floor Completed
Flat - 6 Series - Ground floor to 17th floor completed
Activities in progress
Finishing:
External Plastering Works - 100% completed
Waterproofing Works - 95/104 flats Completed
Tiling - 73/104 Completed
False ceiling - 26 /104 Completed
Door Shutter - 51/104 Completed
Internal Painting Works - 26/104 Completed
-
Tower-C2 Last Updated:31 March 2023 DescriptionTower-C2Activities Completed Structure
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 17th floor Roof Slab completed - 100%
SHR,LMR & OHT works - 100% completed.
Finishing:
Ground floor to 17th floor Block works -100% Completed
Internal Plaster - 104/104 flats completed
Tiling - 58/104 Completed
Internal Painting Works - 22/104 Completed
External Plastering
Flat - 1 Series - Ground floor to 17th floor completed
Flat - 2 Series - Ground floor to 17th floor completed
Flat - 3 Series - Ground Floor to 17th floor completed
Flat - 4 Series - Ground floor to 17th floor completed
Flat - 5 Series - Ground floor to 17th floor completed
Flat - 6 Series - Ground floor to 17th floor completed
Activities in progress
Finishing:
External Plastering Works - Completed
Internal Painting Works in Progress
Internal Painting- 22/104 flats Completed
Tiling Works - 59/104 flats Completed False ceiling - 19 /104 Completed
Waterproofing Works - 101 /104 flats Completed
-
Tower-C3 Last Updated:31 March 2023 DescriptionTower-C3Activities Completed Structure
Raft - 100% completed
Basement Slab roof slab - 100% completed
GF to 17th Floor Roof Slab - 100% completed
SHR, OHT & LMR - 100% completed.
Finishing
Ground floor to 17th floor block work - 100% Completed
Internal Plaster - 105/105 Completed
External Plaster:
Flat - 1 Series - Ground floor to 17th floor completed
Flat - 2 Series - Ground floor to 17th floor completed
Flat - 3 Series - Ground floor to 17th floor completed
Flat - 4 Series - Ground floor to 17th floor completed
Flat - 5 Series - Ground floor to 17th floor completed
Flat - 6 Series - Ground floor to 17th floor completed
Tiling works - 105/105 flats completed
Internal Painting 105 Units Completed
Apts Handing over-105/105 completed
External Painting -1st Coat Paint 100% Completed
External Painting -2nd Coat Paint 100% Completed
Activities in progress
Finishing:
Completed
-
Tower-D1 Last Updated:31 March 2023 DescriptionTower-D1Activities Completed
Structure
Raft - 100% completed
Basement Slab - 100% completed
Ground to 14th Floor Roof slab - 100% completed
SHR, OHT & LMR - 100% completed.
Finishing
Ground floor to 14th Floor Block works - 100 % Completed
Internal Plaster - 88/88 flats completed
External Plastering - 100% Completed
Tiling works - 88/88 flats completed
Apts Handing over - 88/88 completed
-
Tower-D2 Last Updated:31 March 2023 DescriptionTower-D2Activities Completed
Structure
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 14th floor roof slab completed - 100%
SHR, OHT & LMR - 100% completed.
Finishing
Ground floor to 14th Floor Block works - 100% Completed
Internal Plaster - 88/88 flats completed
External Plaster:
Flat - 1 Series - Ground floor to 14th floor
Flat - 2 Series - Ground floor to 14th floor
Flat - 3 Series - Ground floor to 14th floor
Flat - 4 Series - Ground floor to 14th floor
Flat - 5 Series - Ground floor to 14th floor
Flat - 6 Series - Ground floor to 14th floor
Tiling works - 88/88 flats completed
External painting Completed
Internal Painting 88 Units Completed
Apts Handing over-88/88 completed
-
Tower-D3 Last Updated:31 March 2023 DescriptionTower-D3Activities Completed
Structure:
Raft - 100% completed
Basement Slab - 100% completed
GF to 14th Floor Roof slab - 100% completed
SHR, OHT & LMR - 100% completed.
Finishing
1st to 14th floor block work - 100% Completed
Internal Plaster - 87/87 flats completed
Tiling works - 87/87 flats completed
External Plastering - 100% Completed
External Painting - 100% Completed
Apts Handing over - 88/88 completed
-
Tower-D4 Last Updated:31 March 2023 DescriptionTower-D4Activities Completed
Structure:
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 14th floor Roof Slab - 100% Completed
SHR, OHT & LMR - 100% completed.
Finishing
1st to 14th floor block work - 100% Completed
Internal Plaster - 87/87 flats completed
External Plaster:
Flat - 1 Series - Ground floor to 14th floor completed
Flat - 2 Series - Ground floor to 14th floor completed
Flat - 3 Series - Ground floor to 14th floor completed
Flat - 4 Series - Ground floor to 14th floor completed
Flat - 5 Series - Ground floor to 14th floor completed
Flat - 6 Series - Ground floor to 14th floor completed
Activities in progress
Finishing:
Flooring, Grill work - In Progress
-
Tower-D5 Last Updated:31 March 2023 DescriptionTower-D5Activities Completed
Structure:
Raft - 100% completed
Basement Slab - 100% completed
Ground Floor to 14th Floor Roof Slab - 100% Completed
SHR, OHT & LMR - 100% completed.
Finishing
Ground floor to 14th floor block work - 100% Completed
Internal Plaster - 87/88 flats completed
External Plaster:
Flat - 1 Series - Ground floor to 14th floor completed
Flat - 2 Series - 1st to 14th floor completed
Flat - 3 Series - Ground floor to 14th floor completed
Flat - 4 Series - Ground floor to 14th floor completed
Flat - 5 Series - Ground floor to 14th floor completed
Flat - 6 Series - Ground floor to 14th floor completed
-
Tower-D6 Last Updated:31 March 2023 DescriptionTower-D6Activities Completed
Structure:
Raft - 100% completed
Basement Roof Slab - 100% completed
GF to 14th Floor Roof Slab - 100% completed
SHR, OHT & LMR - 100% completed
Finishing
Ground to 14th floor Block work - 100% Completed
Internal Plaster - 74/87 flats completed
-
Tower-D7 Last Updated:31 March 2023 DescriptionTower-D7Activities Completed
Structure:
Raft - 100% completed
Basement Slab - 100% completed
GF to 14th Floor Roof Slab - 100% completed
SHR, OHT & LMR - 100% completed
Finishing
Ground to 14th floor Block work - 100% Completed
Internal Plaster - 58/87 flats completed
-
Block - E Last Updated:Completed DescriptionCompleted
-
Floor Plan
- Tower B1
- Tower B2
- Tower B3
- Tower C1
- Tower C2
- Tower C3
- Tower D1
- Tower D2
- Tower D3
- Tower D4
- Tower D5
- Tower D6
- Tower D7
- GOOGLE MAP
- WALKTHROUGH VIDEO
- Ikea Furnished Home - VIRTUAL TOUR 1
- Ikea Furnished Home - VIRTUAL TOUR 2
Thank you for showing your interest. We will get back to you shortly.
Click Here to Download Brochure -
XXPrivacy Policy
1.ACCEPTANCE OF THE TERMS a. Any visitor logging or navigating on this website automatically agrees to comply with and be bound by the following terms and conditions of use, which govern the relationship with visitors in relation to this web site. All visitors are presumed to have read, understood and agreed to terms and conditions of this site. b. This disclaimer will be governed by and construed in accordance with Indian law, and any disputes relating to this disclaimer will be subject to the jurisdiction of the Courts in Chennai. The visitor warrants that he/she is fully aware of the laws of India. c.Akshaya Pvt. Ltd. can alter or revoke any terms of conditions of this website without notice. The revised disclaimer will apply to the use of our website from the date of the publication. Please check this page regularly to ensure you are familiar with the current version.
2. INFORMATION a. Any visitor logging or navigating on this website automatically agrees to comply with and be bound by the following terms and conditions of use, which govern the relationship with visitors in relation to this web site. All visitors are presumed to have read, understood and agreed to terms and conditions of this site. b. In no event will Akshaya Pvt. Ltd. be liable for any loss or direct or indirect damages arising from the use of or reliance on this web site. Your use of any information or material on this website is entirely at your own risk, for which Akshaya Pvt. Ltd. shall not be liable. It shall be your own responsibility to ensure that any products, services or information available through this website meet your specific requirements. c. The information on this website does not constitute an offer and / or contract of any such type between the owner/developer and the visitor. d. This website contains material which is owned by Akshaya Pvt. Ltd. and is protected by copyright and intellectual property laws. This material includes, but is not limited to, the design, layout, look, appearance, text and graphics. Reproduction is strictly prohibited. e. Akshaya Pvt. Ltd. has the right to alter the information of this website and is under no obligation to communicate any changes.
3. INFORMATION FROM THE VISITORS a. The visitor, by the act of logging onto the website or submitting information through the website or email has consented and expressly and irrevocably authorized Akshaya Pvt. Ltd. to use, analyze, transmit or display all information and documents as may be required by it. The visitor warrants that he has provided true, accurate, current and complete information. By entering a mobile number, user has given consent to Akshaya Pvt. Ltd. to send alerts, promotional SMS and the permission to be contacted. b. In case the visitor does not want to receive information from Akshaya Pvt. Ltd. he will have to communicate to this effect to Akshaya Pvt. Ltd. by sending an email to Customer Cell
4. SECURITY a. Every effort is made to keep the website operative. However Akshaya Pvt. Ltd. takes no responsibility, and will not be liable for, the website or any of its components being temporarily unavailable due to technical issues beyond its control. b. Akshaya Pvt. Ltd. does not warrant that this site will be free of viruses or other harmful components. This website and emails from Akshaya Pvt. Ltd. are vulnerable to data corruption, interception, tampering, viruses as well as delivery error and the visitor accepts liability for any consequences that may arise from them.
5. RESPONSIBILITIES a. Akshaya Pvt. Ltd. or any of its employees, managers or representatives shall not be responsible for any consequential damage or economic loss arising or related to the use of the web site. b. The website may contain links to other websites which are not under control of Akshaya Pvt. Ltd.. Any link to off-site pages or other may be accessed by the visitor at his own risk. Akshaya Pvt. Ltd. has no control over the nature, content and availability of those sites. The inclusion of any links does not necessarily imply a recommendation or endorsement of the views within them. It is the responsibility of the user to examine the copyright and licensing restrictions of linked pages and to secure all necessary permissions.
6. POP-UP ADVERTISEMENTS a. When visiting our web site, your web browser may produce pop-up advertisements. These advertisements are most likely produced by other web sites or by third party software installed on your computer. Akshaya Pvt. Ltd. does not endorse or recommend products or services for which visitor may view a pop-up advertisement on your computer screen while visiting its web site.
-
-
-
-
-
-
-
-
-
-