Activities Completed
Paver Laying around C Block completed
Softscaping around C Block completed
Paver Laying around B Block completed
Children's Play area - Equipment installation, Grantie work & Softscaping work completed
Children's play area - Rubberized flooring Completed
B Block - Statue laying completed
B Block - Water body area granite & Tiling work completed
B Block - Extension works - lower & Upper Basement Slab completed
B Block Extension Paver laying work comleted
C block terrace Solar panel fixing work completed
B Block WPC flooring over podium slab completed
Podium car parking paver work completed
Activities in progress(WIP)
D Block Podium drive way GSB Completed & paver work in progress - 90% Completed
UG sump water proofing work in progress - 95% completed
Hume pipe laying work in progress - D blk completed, work in progress in E block
E Tower - Stilt floor Grano flooring - 65% Completed
E Tower - Water body tiling work completed
E Tower - Sculpture fixing & Enterance granite laying work completed
E Block Podium area - GSB Filling 2/3 completed and Paver work in Porgress - 60% completed
E Block North east side well construction work in progress - 4/4 completed
Podium area Water proofing and Screed concrete work in Progress- D Block Completed & E Block coating 100% work completed
Speed breaker work in progress around B & C Tower
Transformer yard work Pedestral, Pole erection & Painting work completed
DG yard PCC laying work in progress
Basement
Activities Completed
Upper basement Painting work - 80% completed
Upper basement Granolothic flooring - 100% completed
Lower basement RCC retaining wall (In B/W A & B Block) - 100% Completed
Lower basement - PCC purpose soil levelling work is completed
D Block entry Ramp Screed concrete work compeletd
Activities in progress(WIP)
Lower basement - Trench PCC, Blockwork work, Plastering & Cover slab laying in progress - 80% Completed
E Tower - Car parking marking work in progress in upper basement
E Tower - Car parking marking work in progress in lower basement
Fire Fightening Work in Progress, B, C, D Block Completed & E Block in Progress
BW and Plastering in Progress
Lower Basement Screed concrete in Progress - 90% Completed
STP Commissioning work Completed
Upper Basement Final coat painting work in Progress
Lower Basement painting work in Progress - 60% Completed
Lower Basement Corner guard fixing work in Progress